Client : ENGI Co. (An Iranian Investment Company)
Description : Constructing new Refinery with nominal capacity of 60,000 bpsd which is supposed to process the South Pars
gas condensate (API 58)…. The main scheduled products are LPG, Hydro-treated Naphtha, Jet Fuel & Diesel Fuel.
The outline of the main process, utility and offsite Units of refinery are summarized as below :
– Crude Distillation Unit (60,000 bpsd)
– LPG Recovery Unit (3,500 bpsd)
– Naphtha Hydrotreater (41,000 bpsd)
– Kerosene Sweetening Unit (3,100 bpsd)
– Gas Oil Hydrotreater (14,200 bpsd)
– Tankage and Interconnecting Pipeline
Project Location : Assaluyeh (south of Iran)
SEP Scope of Work : Conceptual Design and Bankable Feasibility Study
Status : Completed